Description: A 22 week contract started in January 2012 consisting of the application of insulated render to houses in the Oakley & Kelty areas.
Work carried out as follows:
-
Preparation of walls & application of Alumasc Swisslab Insulated Render to 104 flatted and terraced units.
-
Downpipes replaced with Osma UPVC.
-
Gas flues extended.
All work carried out within a very tight and demanding timescale.